Gas-Lift Troubleshooting

Troubleshoot your well before you call a rig.

Gas-lift problems are usually associated with three areas: inlet, outlet, and downhole (Fig. 1).

Examples of inlet problems may be the input choke sized too large or too small, fluctuating line pressure, plugged choke, etc. Outlet problems could be high backpressure because of a flowline choke, a closed or partially closed wing or master valve, or a plugged flowline.
Downhole problems could include a cutout valve, restrictions in the tubing string, or sand-covered perforations.
Further examples of each problem area are included in this handbook. Often the problem can be found
The Gas-Lift System
Fig. 1: The Gas-Lift System
on the surface. If nothing is found on the surface, a check can then be made to determine whether the
downhole problems are wellbore problems or equipment problems.



Inlet Problems


Choke sized too large

Check for casing pressure at or above design operating pressure. This can cause reopening of upper-pressure valves and/or excessive gas usage. Approximate gas usages for various flow rates are included in Fig. 2.

Choke sized too small.

 Check for reduced fluid production as a result of insufficient gas injection. This condition can sometimes prevent the well from unloading fully. The design gas:liquid ratio can often give an indication of the choke size to use as a starting point.

Low casing pressure. 

This condition can occur because the choke is sized too small, it is plugged, or it is frozen up. Choke freezing can often be eliminated by continuous injection of methanol in the lift gas. A check of injected-gas volume will separate this case from low casing pressure based on a hole in the tubing or cutout valve. Verify the gauge readings to be sure the problem is real.

High casing pressure. 

This condition can occur because the choke is too large. Check for excessive gas usage from the reopening of upper pressure valves. If high casing pressure is accompanied by low injectiongas volumes, the operating valve may be partially plugged or high tubing pressure may be reducing the differential between the tubing and casing.
If this is the case, remove the flowline choke or restriction. High casing pressure accompanying low injection-gas volumes may also be caused byhigher-than-anticipated temperatures raising the set pressures of pressure
operated valves.

Inaccurate gauges.

 Inaccurate gauges can cause false indications of high or low casing pressures. Always verify the wellhead casing and tubing pressures with a calibrated gauge.

Typical Continuous-Flow
Fig. 2: Typical Continuous-Flow
Gas-Lift Operation

Low gas volume.

 Check to ensure that the gas-lift line valve is fully open and that the casing choke is not too small, frozen, or plugged. Check to see if the available operating pressure is in the range required to open

the valves. Be sure that the gas volume is being delivered to the well.
Nearby wells, especially intermittent wells, may be robbing the system. Sometimes a higher-than-anticipated producing rate and the resulting higher temperature will cause the valve set pressure to increase, thereby restricting the gas input.

Excessive gas volume. 

This condition can be caused by the casing choke sized too large or excessive casing pressure. Check to see if the casing pressure is above the design pressure, causing upper pressure valves to be opened. A tubing leak or cutout valve can also cause this symptom, but they will generally also cause a low casing pressure.

Intermitter problems. 

Intermitter cycle time should be set to obtain the maximum fluid volume with a minimum number of cycles. Injection duration should then be adjusted to minimize tail gas. Avoid choking an intermitter unless absolutely necessary. For small gas-lift systems in which opening the intermitter drastically reduces the system pressure, it may be possible to reduce pressure fluctuation by placing a small choke in parallel dead

wells as volume chambers. Check to make sure that the intermitter has not stopped, whether it is a manual-wind or battery-operated model. Wells intermitting more than 200 BFPD should be evaluated for constant low application.  

Less than one barrel per cycle is probably an indication that the well is being cycled too rapidly. 


Outlet Problems 


Valve restrictions. 

Check to ensure that all valves at the tree and header are fully open or that an undersized valve is not in the line (1-in. valve in a 2-in. lowline). Other restrictions may result from a smashed or crimped lowline.  

Check locations where the line crosses a road, which is where this situation is likely to occur. 


High backpressure. 

Wellhead pressure is transmitted to the bottom of the hole, reducing the differential into the wellbore and reducing production. Check to ensure that no choke is in the lowline. Even with no choke bean in a  choke body, it is usually restricted to less than full ID. Remove the choke body if possible. Excessive 90° turns can cause high backpressure and should be removed when feasible. 

High backpressure can also result from parafin or scale buildup in the lowline. Hot-oiling the line will usually remove  parafin; however, removal of scale may or may not be possible, depending on the type. Where high backpressure  is caused by long lowlines, it may be possible to reduce the pressure by looping the lowline with an inactive  line. The same would apply to cases in which the lowline ID is smaller than the tubing ID. Sometimes a partially opened check valve in the lowline can cause excessive backpressure. Common lowlines can cause excessive  backpressure and should be avoided if possible. Check all possibilities, and remove as many restrictions from the system as possible. 


Separator operating pressure. 

The separator pressure should be maintained as low as possible for gas-lift wells. 
Often a well may be lowing to a high or intermediate pressure system when it dies and is placed on gas lift. Make  sure the well is switched to the lowest-pressure system available. Sometimes an undersized oriice plate in the  meter, at the separator, will cause high backpressure. 


Downhole Problems 


Hole in the tubing. Indicators of a hole in the tubing include abnormally low casing pressure and excess gas usage. 
A hole in the tubing can be conirmed as follows:  
1.   Equalize the tubing pressure and casing pressure by closing the wing valve with the lift gas on. 
2.   After the pressures are equalized, shut off the gas input valve and rapidly bleed-off the casing pressure. 
3.   If the tubing pressure bleeds as the casing pressure drops, then a hole is evident. 
4.   The tubing pressure will hold; if not, then a hole is present since both the check valves and gas-lift valves will be in the closed position as the casing pressure bleeds to zero. 
5.   A packer leak may also cause symptoms similar to a hole in the tubing. 


Operating pressure valve by surface closing-pressure method. 

A pressure-operated valve will pass gas until the casing pressure drops to the closing pressure of the valve. As a result, the operating valve can often be estimated by shutting off the input gas and observing the pressure at which the casing will hold. This pressure is the surface closing pressure of the operating valve, or the closing-pressure analysis. The opening-pressure analysis assumes the tubing pressure to be the same as the design value and at single-point injection. These assumptions limit the  accuracy of this method because the tubing pressure at each valve is always varying, and multipoint injection may  be occurring. This method can be useful when used in combination with other data to bracket the operating valve. 


Well blowing dry gas. 

For pressure valves, check to ensure that the casing pressure is not in excess of the design operating pressure, which causes operation from the upper valves. Using the procedure mentioned above, make sure that there are no holes in the tubing. If the upper valves are not being held open by excess casing pressure and no hole exists, then operation is probably from the bottom valve. 

Additional verification can be obtained by checking the surface closing pressure as indicated above. When the well is equipped with fluid valves and a pressure valve on the bottom, blowing dry gas is a positive indication of operation from the bottom valve after the possibility of a hole in the tubing has been eliminated. Operation from the bottom valve usually indicates a lack of feed-in. Often it is advisable to tag bottom with wireline tools to determine whether the perforations have been covered by sand. When the well is equipped with a standing valve, check to ensure the standing valve is not stuck in the closed position.

Well will not take any input gas. Eliminate the possibility of a frozen input choke or a closed input gas valve by measuring the pressures upstream and downstream of the choke. Also, check for closed valves on the outlet side.

If fluid valves were run without a pressure valve on bottom, this condition is probably an indication that all the fluid has been lifted from the tubing and not enough remains to open the valves. Check for feed-in problems. If pressure valves were run, check to see if the well started producing above the design fluid rate because the higher rate may have caused the temperature to increase sufficiently to lock out the valves. If the temperature is the problem, the well will probably produce periodically and then stop. If this is not the problem, check to make sure that the valve set pressures are not too high for the available casing pressure.

Well flowing in heads. 

Several causes can be responsible for this condition. With pressure valves, one cause is port sizes that are too large. This would be the case if a well initially designed for intermittent lift were placed on constant flow because of higher-than-anticipated fluid volumes. In this case, large tubing effects are involved and the well will lift until the fluid gradient is reduced below a value that will keep the valve open. This case can also occur because of temperature interference.

For example, if the well started producing at a higher-than-anticipated fluid rate, the temperature could increase, causing the valve set pressures to increase and locking them out. When the temperature cools sufficiently, the valves will open again, thus creating a condition in which the well would flow by heads. With tubing pressure having a high tubing effect on fluid-operated valves, heading can occur as a result of limited feed-in. The valves will not open until the proper fluid load has been obtained, thus creating a condition in which the well will intermit itself whenever adequate feed-in is achieved. Because an injection gas rate that is too high or too low can often cause a well to head, try tuning in the well.

Gas-lift operation stalls and will not unload. This typically occurs when the fluid column is heavier than the
available lift pressure. Applying injection-gas pressure to the top of the fluid column, usually with a jumper line, will often drive some of the fluid column back into the formation. This reduces the height of the fluid column being lifted and allows unloading with the available lift pressure. This procedure is called “rocking the well.” The check valves prevent this fluid from being displaced back into the casing. For fluid-operated valves, rocking the well in this fashion will often open an upper valve and permit the unloading operation to continue. Sometimes a well can be swabbed to allow unloading to a deeper valve. Ensure that the wellhead backpressure is not excessive or that the fluid used to kill the well for workover was not excessively heavy for the design.

Valve hung open

This case can be identified when the casing pressure will bleed below the surface closing
pressure of any valve in the hole yet tests to determine the existence of a hole show that one is not present. Try shutting the wing valve and allow the casing pressure to build up as high as possible, and then rapidly open the wing valve. This action will create high differential pressure across the valve seat, removing any trash that may be holding it open. Repeat the process several times if required. In some cases valves can be held open by salt deposition.
Pumping several barrels of fresh water into the casing will solve the problem. If the above actions do not help, a flat valve cutout may be the cause.

Valve spacing too wide. 

Try rocking the well when it will not unload. This will sometimes allow working down to lower valves. If a high-pressure gas well is nearby, using the pressure from it may allow unloading. If the problem is severe, the only solution may be to replace the current valve spacing, install a packoff gas-lift valve, or shoot an orifice into the tubing to achieve a new point of operation.

Continuous-Flow Wells 

Unloading a well typically requires more gas volume than producing a well. As a result the input gas volume can be reduced once the point of operation has been reached. Excess gas usage can be expensive in terms  of compression costs; therefore, it is advantageous, in continuous-low installations, to achieve maximum luid production with a minimum amount of input gas. This can be accomplished by starting the well on a relatively small input choke size, at 1/64 increments, until the maximum luid rate is  achieved. 

Allow the well to stabilize for 24 hours after each change before making another adjustment. If for some reason a lowline choke is being used,  increase the size of that choke until maximum luid is produced before  increasing the gas-input choke. If the total gas:liquid ratio (TGLR) exceeds the values shown in Fig. 2, it is possible that too much gas is being used. 

Intermittent-Flow Wells 

In intermittent lift, the cycle frequency is typically controlled by an intermitter. 

Typical Intermittent-Flow  Gas Well Operation
Fig. 3: Typical Intermittent-Flow
 Gas Well Operation
The intermitter opens periodically to lift an accumulated luid slug to the  surface by displacing the tubing with gas. The same amount of gas is required to displace a small slug of luid to the surface as is required to   displace a large slug of luid (Fig 3.). As a result, optimal performance is   Gas Well Operation obtained when the well produces the greatest amount of luid with the least number of cycles. 


The cyclic operation of the injection gas causes the surface casing pressure to luctuate between an opening casing pressure (high) and a closing casing  pressure (low). The difference in the surface opening and closing pressures  during a single cycle is referred to as “spread.” Injection-gas volume per cycle increases as spread value increases.  

To accomplish this, the initial injection-gas volume and the number of injection cycles must be more than required. A good rule of thumb is to   set the cycle based on 2 minutes per 1,000 ft of lift, with the duration of  gas injection based on 1/2 minute per 1,000 ft of lift. Reduce the number  of cycles per day until the most luid is obtained with the least number of   cycles, and then decrease the injection time until the optimal amount of   lequid production is maintained with the least injection time. If one barrel or less is produced per cycle, the cycle time should probably be increased. Be sure the intermitter stays open long enough to fully open the gas-lift valve.                  

This will be indicated by a sharp drop in casing pressure. When a two-pen recorder is used, it will give a saw-tooth shape to the casing pressure line 

(Fig. 4). 



  Troubleshooting: Diagnostic Tools 


   Calculations 


Intermittent Gas Lift: Saw-Tooth Shape to Surface Casing Pressure
Fig. 4: Intermittent Gas Lift: Saw-Tooth
Shape to Surface Casing Pressure

 One method of checking gas-lift performance is by calculating the “tubing load required” (TLR) pressures for each    valve. This can be accomplished by calculating surface closing pressures or by comparing the valve opening    pressures with the opening forces that exist at each valve downhole based on the operating tubing, and casing    pressures, temperatures, etc. Although this method may not be as accurate as a lowing pressure survey because  of inaccuracies in the data used, it can still be a valuable tool in highgrading the well selection for more expensive   diagnostic methods. Weatherford’s VALCAL gas-lift design software is available for this type of diagnostics


  Well-Sounding Devices 

The luid level in the annulus of a gas-lift well will sometimes give an indication of the depth of lift. This method    involves imploding or exploding a gas charge at the surface and uses the principle of sound waves to determine the depth of the luid level in the annulus. Acoustic devices are fairly economical compared to lowing-pressure surveys.  
   It should be noted that for wells with packers, it is possible for the well to have lifted down to a deeper valve while unloading, then return to operation at a valve up the hole. The resulting luid level in the annulus will be below the  actual point of operation. 
   Tagging Fluid Level 
  Tagging the luid level in a well with wireline tools can sometimes give an estimation of the operating valve subject  to several limitations. Fluid feed-in will often raise the luid level before the wireline tools can be deployed down the   hole. In addition, luid fallback will always occur after the lift gas has been shut off. Both of these factors will cause  the observed luid level to be above the operating valve. Care should be taken to ensure that the input gas valve  was closed before closing the wing valve, or the gas pressure will drive the luid back down the hole and below the   point of operation. This is certainly a questionable method. 
   Two-Pen Recorder Charts 
  To calculate the operating valve, it is necessary to have accurate tubing and casing pressure data. Two-pen recorder   charts give a continuous recording of these pressures and can be quite useful if accompanied by an accurate well  test. The two-pen recorder charts can be used to optimize surface controls, locate surface problems, and identify   downhole problems. 
   Flowing Pressure Survey 
   In this type of survey, an electronic pressure gauge or bomb is run in the well under lowing conditions. These   recording instruments can also measure temperature, and both ambient and “quick-response” models are available. 
   Under lowing conditions, a no-blow tool is run with the tools, which prevents the tools from being blown up the hole.  
  The no-blow tool is equipped with dogs, or slips, that are activated by sudden movements up the hole. The bomb is   stopped at each gas-lift valve for a period of time, recording the pressures at each valve. From this information, the  exact point of operation can be determined, as well as the actual lowing bottomhole pressure (BHP). This type of   survey is the most accurate way to determine the performance of a gas-lift well, provided that an accurate well test is  run in conjunction with the survey. The following procedure explains the process in detail.


Procedure for Running a Flowing BHP Test When the Well Is Equipped with Gas-Lift Valves 



Intermittent-Flow Wells 


1.   Install a crown valve on the well if necessary, and low the well to the test separator for 24 hours so that a  
     stabilized production rate is known. Test facilities should duplicate, as nearly as possible, normal production facilities. 
2.   Put the well on test before running the BHP. The test is to be run for a minimum of 6 hours. Test information, two-pen recorder charts, and separator chart should be sent in with the pressure traverse. 
3.   A pressure bomb must be equipped with one, or preferably two, no-blow tools. Use a small-diameter bomb. 
4.   Install a lubricator and pressure recording bomb. Let the well cycle one time with the bomb, just below the  lubricator, to record the wellhead pressure and to ensure that the no-blow tools are working. Rub the bomb,  making stops 15 ft below each gas-lift valve. Be sure to record a maximum and minimum pressure at each  gas-lift valve. Do not shut in the well while rigging up or recording lowing pressures in the tubing. 
5.   Leave the bomb on bottom for at least two complete intermitting cycles. 
6.   High and low tubing and casing pressures should be checked with a deadweight tester or “master test” gauge,  or a recently calibrated two-pen recorder. 





Where to Install a Two-Pen Recorder



Connect Casing Pen Line

• At the well, not at compressor or gas distribution header.
• Downstream of input choke so that the true surface casing pressure is recorded.

Connect Tubing Pen Line

• At the well, not the battery, separator, or production header.
• Upstream of choke body or other restrictions. Even with no choke bean, a less-than-full opening is found in most chokes.

Two-Pen Recorder Installed on Wellhead
Fig. 5: Two-Pen Recorder Installed on Wellhead


from

Weatherford
Handbook

keywords:
gas lift,  Intermittent-Flow Wells, troubleshoot. 

Comments

Popular posts from this blog

Permeability of oil-gas Reservoir Rock

Equilibrium Separation